Resource requirements graphs based on an as-late-as-possible schedule are drawn


A) based on each activity's earliest start time
B) based on each activity's earliest finish time.
C) based on each activity's latest start time.
D) based on each activity's latest finish time.

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

When performing resource-limited scheduling, those activities with highest priority are


A) those activities using the same resource
B) those activities with the least slack.
C) those activities using a different resource.
D) all activities have the same priority.

E) A) and C)
F) A) and D)

Correct Answer

verifed

verified

Resource utilization charts based on each activity's earliest start time are said to be based


A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

Activities drawn in a serial relationship illustrate a


A) resource constraint among the activities.
B) loop format of scheduling the project.
C) laddering format of scheduling the project.
D) technical constraint among the activities.

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to


A) increase costs of all the activities in the project.
B) extend beyond the project completion time.
C) be completed ahead of schedule.
D) increase its requirements for additional resources for all activities.

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified